Force Majeure Clause: Excuse, Notice and the UCC

By Published 9 min read

A force majeure clause excuses a party from performing, or from liability for delay, when a listed event beyond its control prevents performance. Its words decide the events covered, the notice required and what happens if the event lasts. Where a contract has no such clause, UCC 2-615 and CISG Article 79 supply default rules for goods.

What does a force majeure clause do?

A force majeure clause allocates the risk of events neither party controls. It names events, such as natural disasters, war, epidemics or government orders, and says a party prevented by one is not in breach, often on condition of notice and mitigation. Some clauses also allow termination if the event lasts too long.

Clauses differ enough that each one needs reading on its own. These are the parts to identify and record.

PartQuestion it answersVariations to note
Event listWhich events count?A closed list, or a list with a catch-all
CausationMust the event cause the failure, or only affect it?"Prevents", "hinders", "delays"
Control and faultMust the event be beyond the party's control and without its fault?Some clauses add "could not have been avoided by reasonable precautions"
NoticeWho must be told, how and by when?A fixed number of days, or "promptly"
MitigationMust the party try to perform another way?Duty to use reasonable efforts, or none
EffectIs performance suspended, excused or extended?Payment obligations often excluded
TerminationCan either party end the contract if the event lasts?After a set number of days

The "effect" row needs care. A clause that suspends performance during the event does not end the contract, and one that excuses delivery may not excuse payment for goods already delivered. A clause that limits damages for breach, rather than excusing performance, is a different tool, discussed in the post on the limitation of liability clause.

The event list and the catch-all in a force majeure clause

The event list decides whether a force majeure clause applies at all. A closed list covers only what it names. A list followed by a general phrase, such as "or any other cause beyond the party's reasonable control", reaches further, though how far depends on the governing state's rules of interpretation.

A published federal clause shows the usual shape. FAR 52.249-14, Excusable Delays, used in cost-reimbursement, time-and-material and labor-hour government contracts, says the contractor shall not be in default because of any failure to perform if the failure arises from causes beyond the control and without the fault or negligence of the contractor. Its examples are acts of God or of the public enemy, acts of the government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes and unusually severe weather. In each instance, the failure must be beyond the contractor's control and without its fault or negligence.

The same clause deals with subcontractors in a way private clauses also have to address. A failure caused by a subcontractor's failure is excused only if the cause was beyond the control of both and without the fault of either, unless the subcontracted supplies or services were obtainable from other sources, the contracting officer ordered the contractor in writing to buy from another source, and the contractor failed to comply reasonably. On the contractor's request, the contracting officer ascertains the facts and extent of the failure, and if an excusable cause is found, the delivery schedule is revised, subject to the government's rights under the contract's termination clause.

Three questions to ask of any event list:

  1. Is the event named? If an epidemic, a government order or a cyberattack is named, coverage is clearer than if it must fit a general phrase.
  2. Does the clause exclude anything? A clause may say that changes in market price or a party's financial difficulty are not force majeure events.
  3. Whose events count? A supplier's own supplier failing may or may not qualify, depending on the wording about subcontractors.

When a contract has no force majeure clause: UCC 2-615

For sales of goods, UCC section 2-615 excuses a seller's delay in delivery or non-delivery when performance as agreed has been made impracticable by a contingency whose non-occurrence was a basic assumption of the contract, or by good-faith compliance with a governmental regulation or order. The seller must allocate fairly among customers and notify buyers seasonably.

The text of UCC section 2-615 opens with a qualification that links it to the contract's own terms: it applies "except so far as a seller may have assumed a greater obligation". A force majeure clause can therefore narrow or widen the excuse, and a seller that promised delivery regardless of circumstances may have assumed the greater obligation.

The section has three paragraphs:

  • (a) The excuse. Delay or non-delivery is not a breach if performance has been made impracticable by the occurrence of a contingency the non-occurrence of which was a basic assumption on which the contract was made, or by compliance in good faith with any applicable foreign or domestic governmental regulation or order, whether or not it later proves to be invalid.
  • (b) Allocation. Where the cause affects only part of the seller's capacity, the seller must allocate production and deliveries among its customers, and may include regular customers not then under contract and its own requirements for further manufacture, in any manner which is fair and reasonable.
  • (c) Notice. The seller must notify the buyer seasonably of the delay or non-delivery and, when allocation is required, of the estimated quota available to the buyer.

A related rule covers smaller failures. Under UCC section 2-614, where without fault of either party the agreed loading or unloading facilities fail, an agreed type of carrier becomes unavailable, or the agreed manner of delivery becomes commercially impracticable, a commercially reasonable substitute must be tendered and accepted if one is available.

Article 2 governs transactions in goods. Service agreements without a force majeure clause fall to the governing state's general contract law on impossibility, impracticability or frustration, which this post does not survey.

What notice does a force majeure clause require?

A force majeure clause may require notice of the event within a fixed period, given as the notices clause requires. Whether late notice costs the excuse depends on the wording. For goods, UCC 2-615(c) requires seasonable notice by the seller; CISG Article 79(4) makes a party liable for damages from the other's failure to receive notice in time.

The notice provision is the one part of a force majeure clause that starts a clock. When an event begins, the questions are the same as for any contractual notice:

  • What must the notice say: the event, its expected duration, the obligations affected, the steps taken to mitigate?
  • By when: a number of days from the event, from the party's knowledge of it, or "promptly"?
  • By what method and to which address, under the notices clause and any later change of address?
  • Must updates follow at intervals, and must the party give notice when the event ends?
  • Does the clause make timely notice a condition of the excuse?

The buyer's side of the UCC rule appears in UCC section 2-616. When a buyer receives notification of a material or indefinite delay or an allocation justified under section 2-615, it may by written notification to the seller terminate and discharge any unexecuted portion of the contract as to the delivery concerned, or modify the contract by agreeing to take its available quota. Where the deficiency substantially impairs the value of the whole contract, the buyer may do the same as to the whole. If the buyer fails to modify the contract within a reasonable time not exceeding thirty days, the contract lapses with respect to any deliveries affected. The section's provisions may not be negated by agreement, except so far as the seller has assumed a greater obligation.

That thirty-day limit runs against the buyer. Under subsection (2), a buyer who receives the seller's notification and does not modify the contract within that time finds the contract lapsed as to the affected deliveries.

Force majeure in international sales: CISG Article 79

Where the UN sales convention governs a sale of goods, Article 79 exempts a party from liability for a failure to perform if it proves the failure was due to an impediment beyond its control that it could not reasonably have taken into account at contracting or avoided or overcome. The exemption covers damages only, while the impediment lasts.

The Convention's text, published by UNCITRAL, sets out five paragraphs in Article 79:

  1. The test. A party is not liable for a failure to perform any of its obligations if it proves that the failure was due to an impediment beyond its control and that it could not reasonably be expected to have taken the impediment into account at the time of the conclusion of the contract, or to have avoided or overcome it or its consequences.
  2. Third parties. If the failure is due to a third person engaged to perform the contract, the party is exempt only if it is itself exempt and the third person would be exempt if the article were applied to it.
  3. Duration. The exemption has effect for the period during which the impediment exists.
  4. Notice. The party who fails to perform must give notice of the impediment and its effect on its ability to perform. If the notice is not received within a reasonable time after the party knew or ought to have known of the impediment, it is liable for damages resulting from such non-receipt.
  5. Other remedies. Nothing in the article prevents either party from exercising any right other than to claim damages under the Convention.

Paragraph (5) is the difference that matters most in practice. An excused seller under Article 79 is not liable for damages, but the buyer may still have other rights under the Convention, and the contract's own force majeure clause may say something different. Article 6 of the Convention lets parties derogate from or vary its provisions, so the contract's own clause may displace or add to Article 79. Whether the Convention applies at all is discussed in the post on the battle of the forms.

Reviewing force majeure clauses across a contract portfolio

When a wide event strikes, such as a regional disaster or a sweeping government order, a legal team needs every force majeure clause that might apply, whether the company or its counterparties might invoke it. The useful record for each contract is the event list, the notice deadline and method, the mitigation duty and the termination trigger.

A sequence that works when time is short:

  1. Identify the contracts. Start with those performed in the affected place or dependent on affected suppliers, then the largest by value.
  2. Read each clause with its definitions and notices clause. Record whether the event is named, whether a catch-all could reach it, and what the clause excludes.
  3. Diary every notice deadline. For the company's own notices and for any response period, such as the thirty days in UCC 2-616 for a buyer of goods.
  4. Record what was sent and received. Each notice, its date, method and proof of delivery, filed with the contract.
  5. Track the end of the event. Some clauses require notice when the event ends, and termination rights may depend on how long it lasted.

Steps 1 and 2 depend on finding the right contracts quickly, which is the job of a well-kept repository; the fields to record are set out in the post on contract repository software. Reading the same clause in many contracts and putting the answers into one table is the subject of the post on AI clause extraction, which also explains how to check each extracted cell against the page.

If a force majeure dispute reaches litigation, the event's timeline, the notices and the correspondence become the evidence. Lucerna Law answers questions about a matter's files, each answer cited to the file it came from, and the product section of the home page shows the kinds of question it is asked. Whether a particular event excused a particular failure is a question of law and fact for counsel in the matter.